The turtle at Riverside’s Turtle Park is being bestowed with a new name.
Starting on Aug. 21, the parks and recreation department asked residents to submit potential names for the park’s eponymous turtle statue. After two rounds of voting, a name has been chosen: Junior.
Ron Malchiodi, the director of parks and recreation, said the name was submitted by a 7-year-old resident, Lucy Sifuentes, as one of more than 250 total submissions through an online survey, which closed on Sept. 4.
“We also went straight to our experts. We asked children in our programs for their suggestions as well, some of which were very entertaining,” Malchiodi said.
He said he and other staffers who formed the Turtle Committee narrowed those submissions down to 12 semifinalists, which were cut down to six finalists in a first-round vote in September.
In the final round vote in October, Junior won with 112 votes. The runner-up name was Shellborne, Malchiodi said, which earned 60 votes.

Malchiodi announced the name at the Nov. 19 board of trustees meeting.
“It does have significance,” he said. “The original turtle at Turtle Park was donated by the Riverside Junior Women’s Club.”
In honor of her winning submission, Malchiodi said Lucy will be recognized at the park’s reopening following planned reconstruction to improve the playground.
Unfortunately, that reopening ceremony won’t take place this year as originally thought. Later in the Nov. 19 meeting, trustees approved a change order for the expected substantial completion date for the project from Oct. 30, 2026, to May 31, 2027, with the final completion shifting from Dec. 4, 2026, to June 21, 2027.
“On Aug. 20, a purchase order was approved for the playground equipment through Kompan, Inc. The order was confirmed the following day, and we waited for a confirmed delivery date, as the items were custom,” Malchiodi said. “Unfortunately, when the date was confirmed, it was for Dec. 31, which is outside of our original timeline and would push construction to early spring of 2027.”
Malchiodi said the change order trustees were considering did not include any changed costs. While he said not to “anticipate any significant cost increases,” Malchiodi said the village’s construction contractors won’t be able to give a new final price until 2027. Any increase in the cost would come before the village board for approval in the form of another change order, he said.
“While we had hoped to start this year, the good news is that the playground will still be ready for use this summer,” Malchiodi said. “Since the project was likely to saddle seasons, this will eliminate construction fencing and equipment out there throughout the winter.